Since 2020, Knowle Grange Health Club has built a new purpose-built gym, extended its spa, changed its access and more than trebled its permitted membership, from 150 to 450. None of that could happen without planning permission, and all of this has been achieved using the same project team. Six years and eight permissions later, it is a good example of what ongoing planning support actually looks like for a growing business.

Christine Dadswell, now an Associate in Batcheller Monkhouse’s Planning & Development team, has advised Knowle Grange’s spokesperson throughout. The relationship began in 2020, while Christine was working at another firm, ASP, and it has continued without a break since she joined Batcheller Monkhouse. For a business that has needed almost continuous planning input, that continuity has counted for as much as the advice itself: every new application has built on an adviser’s existing knowledge of the site, the council and the specific planning constraints and parameters of the site, rather than starting from a blank page.

The first permission, granted in 2021, allowed the spokesperson to demolish an old barn and build a new gym, extend the main health club building, add a pool changing room and bring a greenhouse into use as part of the club, with membership capped at 150. A follow-up application refined the details already agreed: a change to the external materials and a revised roof pitch on the gym and changing rooms.

The bigger test came in 2023, when the spokesperson wanted to more than treble that membership cap, from 150 to 450. Growth on that scale is not just a question of buildings, it changes the traffic the site generates too. Christine’s team had to demonstrate the highways impact of significantly more members and vehicles, close the existing accesses, create a new one and provide the extra parking a much larger membership requires. The council’s condition for agreeing to the increase was a contribution towards upgrading the local bus stop.

WhenReferenceWhat it achieved
2021 (ASP)WD/2021/0002/FNew gym building, health club extensions, pool changing rooms and greenhouse conversion; membership capped at 150.
2021 (ASP)WD/2021/2811/FAAmended external materials and roof pitch on the gym and changing rooms.
2023 (BM)WD/2023/1056/FNew maintenance building for the health club.
2023 (BM)WD/2023/1419/FMembership cap raised from 150 to 450; new vehicular access and additional parking.
2024 (BM)WD/2024/0572/NMAParking resurfaced in Kentish ragstone; cycle shed replaced with Sheffield stands.
2024 (BM)WD/2024/0876/CDConditions attached to the 2023 membership increase discharged.
2025 (BM)WD/2025/0739/FRear extension with pitched roof to the existing utility room.
2026 (BM)WD/2026/0634/FConstruction of a garden room.

Working Within the Council’s Limits

Not every part of the site has been equally open to new building. The council has been clear about where it will and will not accept additional built form, and part of Christine’s role has been steering each proposal, from a garden room to a utility room extension, towards the areas where the council is comfortable seeing more development. It is a good illustration of what much planning work for growing rural and leisure businesses looks like in practice: not one large application, but a series of smaller, carefully targeted ones, each building on the permission before it.

“We have enjoyed an excellent working relationship with Christine Dadswell over the years. She has successfully handled various planning applications for Knowle Grange Health Spa during our programme of major refurbishment. The advantage of having a long-term relationship with a planning adviser, such as Christine, is that she knows Knowle Grange well, including its planning history. We have found that to be very helpful and time-saving. She also fights our corner rather than push us to go with what may suit the planners best.”
– Spokesperson, Knowle Grange

What This Means for Other Growing Businesses

Eight permissions in six years is not typical, but it does show what is possible when planning advice keeps pace with a business as it changes. Knowle Grange’s plans did not stop once the first permission was granted, and having an adviser who already understood the site meant each new stage could move faster than it would starting from scratch with a different adviser.

If your business has planning permissions that need revisiting as it grows, or you are not sure whether your current use, membership numbers or access arrangements still match what was originally approved, talk to our Planning team before you make changes on the ground.